Project Duration Calculator.

Estimate project duration from work quantity, productivity and crew count.

Connected to Zektrx

Project ManagementScheduling

Use this result as a planning estimate, then create controlled Zektrx records for tasks, templates, evidence, actions, pricing and delivery.

units
units/day
crews
%

Instant Results

Estimated duration

5.5days

Duration including non-working allowance.

Net working days

5.0days

Duration before allowance.

Explanation

What this calculates

The calculator divides total work by daily crew output, then applies an allowance for non-working time.

Formula

Days = quantity / (productivity x crews) x (1 + non-working %)

Inputs are validated on screen and converted where unit options are available.

Worked Example

Example result

1,000 units at 100 units/day with 2 crews and 10% allowance gives 5.5 days.

FAQ

Calculator questions.

Does this replace a programme?

No. It is an estimating check. Real programmes need dependencies, access, procurement and resource logic.

Can I use hours instead of units?

Yes, as long as the productivity rate uses the same unit basis.